COMPANY: Sigur Ros Turkmenistan
PROJECT TITLE: Petronas Turkmenistan Block 1 Gas Development Project
CLIENT: PETRONAS Turkmenistan
LOCATION: Turkmenistan
YEAR: 2009-2011
VESSEL: Derrick Lay Barge (DLB) Armada Installer
SCOPE OF WORK:
MY INVOLVEMENT:
I was only invovled in the loadout of the PLEM onto a Supply vessel at Turkmenbashi Port
INTRODUCTION
Petronas Carigali (Turkmenistan) Sdn Bhd (COMPANY), a wholly owned exploration and production subsidiary of PETRONAS, has entrusted Malaysia Marine and Heavy Engineering Sdn Bhd (MMHE) and Technip Geoproduction (M) Sdn Bhd (CONTRACTOR) to undertake the development of the Onshore Gas Terminal (OGT) and Magtymguly field which are located in Block 1 offshore of Turkmenistan (referred to as PETRONAS CARIGALI TURKMENISTAN BLOCK 1 GAS DEVELOPMENT PROJECT- hereinafter referred to as the “PROJECT”).
The Turkmenistan Block 1 field is an elongated field approximately 50 to 60 km long and 10 km wide offshore Turkmenistan. The Block 1 deposits will be accessed using a phased development plan sufficient to maintain a substantial flow rate for a number of years.
CONTRACTOR has subcontracted part of the PROJECT to Sigur Ros Sdn Bhd (SGRSB) (SUBCONTRACTOR) to perform the “WORK” as specified in the subcontract.
SUBCONTRACTOR will undertake the WORK for the following FACILITIES to be developed under the PROJECT for Phase 1A:
- Export submarine pipelines from Magtymguly (MCR-A) to Kiyanli OGT (separate gas and condensate pipelines, inclusive of pre-installed pipeline risers at MCR·A):
– 26″ dia. gas export pipeline, approximately 73km in length.
– 12″ dia. condensate export pipeline, approximately 73km in length. - MEG supply pipeline from Kiyanli OGT to Magtymguly (MCR-A) (inclusive of the pre installed pipeline riser at MCR-A):
– 4″ dia. MEG supply pipeline, approximately 73km in length (this line will piggyback on the 12″ dia. condensate pipeline). - Condensate loading pipelines from the OGT to the SPM buoy:
– 2 x 12″ dia. condensate loading pipelines, approximately 7km in length each. - SPM buoy, complete with mooring system, risers and PLEM (engineering and procurement by others).
The signing entities for the SUBCONTRACT are between MMHE and SGRSB.
LOADOUT AND TRANSPORTATION
INTRODUCTION
The Single Point Mooring System comprising of Anchor piles, Anchor Chain, PLEM and Submarine hose and other miscellaneous items have been fabricated at the following fabrication yard:
SPM system & PLEM:
Gulf Piping Co. Fabrication Yard by Bluewater Engineering Services (BES)/MMHE Mussaffa, Abu Dhabi
Pile : TBA
PRE-LOADOUT
Prior to loadout from the Kiyanly yard, inspection list shall be with referenced to SR·TKM·OPR· PLEM·SPM·S104, Loadout Coordination Manual for SPM and PLEM and also included in No. SR·TKM· OPR·PLEM·SPM-S1 00, PLEM and SPM Buoy System Transportation Study will be reviewed and completed. Any areas of potential concern will be highlighted to company’s. The loadout is also detailed in the above document.
LOADOUT AND TRANSPORTATION
Loadout list for the transportation barge for SPM System and PLEM is shown in the Document No. SR-TKM-OPR-PLEM-SPM-S100
General arrangement and seafastening details for loadout of the pipeline and miscellaneous items are also included in the above report.
The SPM system and PLEM components will be loadout to the installation site on the following transportation barge:
Transportation Barge | Component | Quantity |
TBA BARGE 1
(lxWxD) |
Anchor Piles (1219mm Dia. x59ft lgth)
Anchor Chains (73mm Dia 886ft lgth) Chaser Pile (1219mm Dia. X 59ft lgth) Chaser Rack frame |
4 lgth
4 nos 1 lgth 1 no |
TBA BARGE 2 (LX W x D) | Anchor Piles (1219mm Dia. x59ft lgth)
Anchor Chains (73mm Dia 886ft lgth) Submarine hoses PLEM |
2 lgth
2 nos 1 lgth 1 no |
TBA vessel Lx W x D | SPM Turret Buoy
Floating hoses Mooring hawser assembly |
1 no
1 lgth 1 lgth |
A detailed review of all components and material loaded out will be conducted and checked against the loadout list as described in the Loadout Coordination Manual. Any discrepancies in the quantity and conditions of the SPM System & PLEM strcuture will be highlighted to company representative and recorded prior to transfer of custody of the transportation barge to subcontractor. A loadout and tie-down arrangements of strcutures on the transportation barge are shown in Fig. 2.3-1 and 2.3-2 respectively.
The tie-down and loadout arrangements for the subsequent voyages are detailed further in Document No: SR-TKM-OPR-PLEM-SPM-S100, PLEM and SPM Buoy System Transportation Study
Prior to departure of each transportation barge from the respective loadout location, a three(3) day weather outlook will be obtained from the Meteorological Service and forwarded to the tug boat captain for his further action. Shelter and safe tow route shall be identified and briefed to the Tug Master by the Marine Captain
PIPELINE END MANIFOLD (PLEM) INSTALLATION
INTRODUCTION AND KEY INFORMATION
This section details out the proposed method for the installation of PLEM near SPM system at approximately KP 7.099. DSV will be utilized for the PLEM installation work. PLEM installation will commence after completion of 2 x 12″ dia. Pipeline installation from OGT to SPM. Four points lifting with spreader bar will be used to lift up the PLEM from transportation barge and lower down to proposed location. Throughout the installation activities, ROV will be deployed to monitor PLEM lowering and setting activities.
PLEM shall be fabricated in Gulf Piping Co. fabrication yard by Bluewater Engineering Services (BES)/MMHE in Mussaffa, Abu Dhabi. The 179ft Class Transportation Barge shall be utilized to transport PLEM to MMHE Kiyanly.
DSV will be set-up with ‘4’ point mooring and her starboard side will facing the proposed PLEM location. Refer to Fig. 5.1·1 for barge set-up for PLEM installation.
DESCRIPTION OF PLEM
Designation : Gravity Based Foundation Pipeline End Manifold (PLEM)
Designed Weight : Approximately 101.5 MT (Including concrete block weight and piping insulation)
Field : Approximately 7 km West from the Onshore Gas Terminal (OGT) at Kiyanly, Turkmenistan
Proposed Centre Coordinate : E 643 695.64 m N 444 8557.93m
Water Depth : Approximately 20 m
Nominal Installation Coordinates PLEM
Description |
Bearing (deg.) | Easting (m) |
Northing (m) |
PLEM Flange Centre |
260.5 | 643 695.96 | 4 448 557.93 |
PLEM tie·in North |
260.5 | 643 700.40 |
4 448 561.00 |
PLEM tie-in South | 260.5 | 643 701.16 |
4 449 556.47 |
PLEM INSTALLATION TOLERANCE
PLEM installation tolerance are as per the following figures:
– Within± 1.5m radius offset PLEM C.O.G
– Within ± 2° orientation
– Within ± 0.1m vertical displacement
MATERIALS
Refer to section 3.6 for PLEM materials & equipment details.
PREPARATORY WORK
- Deploy ROV to perform debris survey on the PLEM proposed installation
- Prepare rigging required for PLEM i.e. wire rope slings and shackles. Ensure lifting rigging is in good condition and come with valid certificates. Refer Fig. 5.5-1
- Bring alongside PLEM transportation barge to portside of the Refer to section 2 for PLEM arrangement on the transportation barge.
- Transfer personnel to PLEM transportation barge e. welders, fitters, rigger and scaffolders for preparation work to cut PLEM tie-down seafastening. Refer to Fig. 2.3-2 for tiedown seafastening drawings.
- Transfer lifting rigging to the PLEM transportation Rig-up lifting rigging to the PLEM as per Fig. 5.5-2 Connect necessary tag lines for PLEM orientation and setting.
- Paint all edges of the PLEM and mark corners A, B, C, and D for easy
- Attach control tugger lines to PLEM for orientation
- Install a high powered USBL beacon at the ROV and two numbers on the lifting sling
- Test and calibrate all electronic equipment including USBL beacons and ROV tracking
- Ensure beacons are complete with extended life battery pack (freshly charged).
- Prepare rigging required for PLEM concrete block base i.e. wire rope slings and shackles. Ensure lifting rigging is in good condition and come with valid certificates. Refer Fig. 5.5-3
- Transfer lifting rigging to the PLEM transportation Rig-up lifting rigging to the PLEM Concrete block base foundation and connect necessary tag lines for PLEM orientation and setting. Refer Fig 5.5-4 and 5.5-5
PLEM INSTALLATION
The PLEM will be positioned with reference to the surveyor’s navigation screen and ROV. The positioning and orientation of the PLEM will be monitored using ultra short baseline (USBL) acoustic positioning system
Two survey transponders/high-powered beacons will be installed at the PLEM frame to mark the corridor/window. The ROV will be used to provide visual display setting of the PLEM. A third survey beacon will be installed on the ROV in order to provide a check on the PLEM position prior to release it. A check on the survey system will be done to ensure USBL beacons are referring to the same coordinate system as the barge navigation system.
- Set-up DSV as per 5.1·1
Safety Note: SUBCONTRACTOR Marine Capt. (MC) and Offshore Construction Supt. (OCS) to ensure proper coordination and communication between anchor handting tugs and main work barge during anchor handling activities and ensure all survey 8: positioning equipment in working condition and calibrated. Reference for anchor positioning shall be made to the appr·oved anchor patterns and pre-lay survey report by SUBCONTRACTOR. Limiting weather criteria specifications for all activities will be at SUBCONTRACTOR OCS discretion and governed by Company’s Marine Guidelines of permitted operations. - ROV will be deployed to examine the seabed conditions i.e. scar marks, depressions, etc. Any debris shall be removed from the PLEM proposed location either using ROV or divers. Refer to Fig. 5.6·1 for PLEM footprint and debris survey.
- Meanwhile inspect the PLEM rigging and check against drawing lifting Refer to Fig. 5.5-2
- Install tugger lines at 2 locations on the PLEM and install taglines to control the PLEM orientation during initial lifting from the barge
- Surveyor will determine a target location calculated for the position, enter it into the navigation software and shown of the navigation display
- Lift up the PLEM using DSV crane and lower it down until approximately 5m off the Refer Fig. 5.6·3
- ROV will constantly monitor the lowering process of the PLEM to the target laydown
- Once the PLEM has been orientated to the correct heading within the target location, then it can be lowered down to the
- ROV will take fixes on 4 corners of the This is to double check the position and orientation given out by the beacons.
- Upon confirmation by the Field Engineer and Surveyor and acceptance by Client Site Diver will remove the riggings from the PLEM by unshackle the four points lifting slings from PLEM padeyes.
- Disconnect/remove all control tugger lines from PLEM frame and recover to ROY to perform as built installation video survey on the newly installed PLEM.
- Prepare for the next installation work
PLEM Concrete Block Base Foundation Installation
- PLEM concrete block shall be install upon completion of submarine hose, control umbilical and hydraulic/electric jumper hose installation
- 2 nos, 12T and 8 nos, 5T of concrete block will be located on the PLEM for the foundation base of the Refer Fig.5.5-3 and Fig 5.5-4 for the details of the concrete block and Fig. 5.6.1·2 proposed location to install.
- 4 Point lifting will be used to lifting concrete block from the transportation barge to the installation proposed Refer Fig. 5.5·5
- The method and DSV setup for the concrete block installation will be similar as PLEM installation sequence